5 East Street and 2-6 Cowper Street, Granville

Project Overview

We are seeking community feedback on a proposed mixed used development at 5 East Street and 2-6 Cowper Street, Granville. Ellipse Property, the developer, has commissioned HillPDA to explain the project to the community and gather feedback as part of the State Significant Development Application (SSDA).

We are holding two online engagement sessions on Monday 30 November from 12:30-1:30pm and Wednesday 2 Decemberfrom 5:30-6:30pm. Please register using the link to the right (if viewing on desktop) or below (if viewing on phone) to attend either session. There will be time for Q&A in the session if you want to ask questions.

Please provide your feedback by Friday 11December 2026.

Project information

Crane with solid fill

About the proposal

The proposal is a mixed use development, incorporating:

  • A 32 storey building (112m), including 1 excavated basement level of parking, commercial ground floor, 4-storey podium as parking and residential above the podium 
  • At least 344 units (10% of these will be affordable housing units to be managed by a registered community housing provider for at least 15 years)
  • Approximately 90 co-living units, maintained by a managing agent
  • Private communal open space on levels 5 (top of podium) and 31 (top of building)

Project benefits

The site is located close to GranvilleTrain Station and the commercial centres of Granville, and with nearby access to Parramatta Road and the M4 Western Motorway.

The project will contribute housing supply, including subsidised affordable housing.

  • Project scoping

    The SSDA (State Significant Development Application) scoping phase is the mandatory first step to the project approval process. During this phase, the developer submitted a scoping report to the NSW Department of Planning, Housing and Infrastructure (DPHI) to get Secretary's Environmental Assessment Requirements (SEARs). The SEARs dictated the exact technical studies required for the Environmental Impact Statement (EIS).

  • SSDA preparation

    As part of the SSDA, the developer prepares an EIS. It outlines information on the economic, environmental, and social impacts of the project. It also outlines how the project will minimise or eliminate these impacts. For this project, the developer and their consultants are preparing detailed traffic, visual and noise impact assessments plus many others as part of their EIS. 

    A key part of preparing the EIS requires seeking feedback from the community. The developer has appointed HillPDA to do this work to ensure it is fair, objective and informative. HillPDA is explaining the project to the community, asking for feedback, and collating the feedback into an Engagement Report as part of the EIS. The EIS will inform the next stage of the project. 

    When all the technical assessments of the EIS are complete, the developer will submit the SSDA to the Department. This is the formal lodgement.

  • Public exhibition

    After formal lodgement of the SSDA, including the completed EIS and Engagement Report, DPHI will publicly exhibit the project for 28 days. At this point, the community can make formal submissions to DPHI on whether they support the project or if they have comments about the proposal.

  • Project determination

    After the public exhibition period, DPHI will review the proposal along with all public submissions and request the developer to respond to all submissions.

    DPHI will then make their final assessment.